How to evaluate material delivery performance based on standard reports?

$
0
0

Hi

 

In my organisation we have discussions that material is not deliverd on time ordered through a PM Work Order. I would like to evaluate the performance to get a objective analysis. My first thoughts are:

 

- Take a list of released work orders in a certain period (e.g. last month)

- LIst the materials used on those work orders

- Compare the requested delivery date for the material (on PR) with the PO creation Date and Goods Receipt Posting Date.

 

Since there is no standard report for it, what reports could i use to combine for this analysis?

 

Many thanks

 

Felix