Finished material cost is zero in process order confirmation

$
0
0

Dear All,

We have done planning in projects system on wbs element and then we run mrp and generate planned orders

and then convert in process order and release it.

 

then we do process order confirmation but in accounting entry for all raw material have some cost but finished material stock up with zero value.

but we require with value .

 

Please do the need full help.

 

Regards

Mahendra